This is information on that Function 79 from TIWO 86376:
Chad has requested a new function for the RF Scanner that would allow the material handlers to run the older version of Verify load if they need to redo a truck.
This came about because in Kenton, they had to have a trucker come back in to have the load redone. Since the driver had pulled all of the tags already, the only way to redo the load is to verify all of the tags again. In order to do this, they want to be able to scan all of the tags and validate that the load is still correct by content with the changes that are also being made.
Here is what I have so far for the New Scanner function 79. (Reload Verify).
If the plant is not turned on for the new verify process, then function 79 will not even be an option.
When it is available, it will exercise the following behaviors:
-When 79 is selected, the material handler will need to enter the load-id and truck number, this allows the program a way to check to see if it has ran process 30 already.
-If process 30 has already been used and the load was successfully verified, the material handler will have the option to proceed with a second verification and be able to scan tags like the old verify load process works.
-If process 30 has already been used and the load was NOT successfully verified, the material handler would be redirected to the new verify load process (30) and not allowed to scan tags.
-If process 30 is not completed, the material handler would be redirected to the new verify process (30), and not allowed to scan tags.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article